Eskişehir Cement Plant Automation & Electrification

  • Customer:Eskişehir Çimento
  • Category:Process
  • Date:12 December, 2017
  • Status:Commissioned
  • Application:Cement
  • Control System:ABB 800xA DCS
  • Size:2 Controller & 2.100 I/0

Project Details

The project is a turnkey project including process control and automation of the plant, LV-MV electrification and instrumentation together with the packaging systems of the grinding plant with the capacity of 100 t/h. As INSOTECH, we built a cement focused library based on ADVANT version of BMI library from ABB. That library is so-called INBMI library which allows group operations of the devices in that grinding plant in automation. The execution time of the project is six months, and one-month of it covers the operation handled by the INSOTECH team.